Colorado Springs issued the following announcement on Sept. 14.
We have a quick overview of 2C paving and concrete work that's taking place right now in Colorado Springs..
Week of 9/14/2020
Crews will continue milling and paving operations on the following segments:
STREET | FROM | TO |
FLINTRIDGE DR | ACADEMY BLVD | DEAD END |
FLINTRIDGE DR | VICKERS DR | MONTEBELLO DR |
JET WING DR | FOUNTAIN BLVD | ASTROZON BLVD |
NEVADA AV *Phase 2 | FILLMORE ST | *ROCK ISLAND TRAIL BRIDGE |
STREET | FROM | TO |
MESA RD | FILLMORE ST | UINTAH ST |
MESA RD | UINTAH ST W | WALNUT ST |
CASCADE AV | DEAD END | FILLMORE ST |
VERDE DR | CIRCLE DR | CHELTON RD |
PIKES PEAK AV | MURRAY BLVD | FROST LN |
STREET | FROM | TO |
CASCADE AV | UINTAH ST | PLATTE AV |
STREET | FROM | TO |
UNION BLVD | WOODMEN RD | ACADEMY BLVD |
PLATTE AV | UNION BLVD | WAHSATCH AV |
WESTMEADOW DR | CHEYENNE MEADOWS DR | ACADEMY BLVD |
CHEYENNE MOUNTAIN BLVD E | ROUND-A-BOUT | SH115 |
Crews completed the concrete operations on the following segments:
STREET | FROM | TO |
FLINTRIDGE DR | ACADEMY BLVD | DEAD END |