Colorado Springs issued the following announcement on Sept. 14.

We have a quick overview of 2C paving and concrete work that's taking place right now in Colorado Springs..

Week of 9/14/2020

Crews will continue milling and paving operations on the following segments:

 STREET

FROM

TO

FLINTRIDGE DR

ACADEMY BLVD

DEAD END

FLINTRIDGE DR

VICKERS DR

MONTEBELLO DR

JET WING DR

FOUNTAIN BLVD

ASTROZON BLVD

NEVADA AV *Phase 2

FILLMORE ST

*ROCK ISLAND TRAIL BRIDGE

Crews anticipate beginning milling and paving operations on the following segments:

 STREET

FROM

TO

MESA RD

FILLMORE ST

UINTAH ST

MESA RD

UINTAH ST W

WALNUT ST

CASCADE AV

DEAD END

FILLMORE ST

VERDE DR

CIRCLE DR

CHELTON RD

PIKES PEAK AV

MURRAY BLVD

FROST LN

 Crews anticipate completing concrete operations on the following segments:

 STREET

FROM

TO

CASCADE AV

UINTAH ST

PLATTE AV

 Crews will continue concrete operations on the following segments:

 STREET

FROM

TO

UNION BLVD

WOODMEN RD

ACADEMY BLVD

PLATTE AV

UNION BLVD

WAHSATCH AV

WESTMEADOW DR

CHEYENNE MEADOWS DR

ACADEMY BLVD

CHEYENNE MOUNTAIN BLVD E

ROUND-A-BOUT

SH115

Week of 9/7/2020

Crews completed the concrete operations on the following segments:

 STREET

FROM

TO

FLINTRIDGE DR

ACADEMY BLVD

DEAD END

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS